Interstate 70 from Route 94 to Mid Rivers Mall Drive – resurfacing. This work is expected to start in spring 2011 and finish by summer 2011.
Interstate 70 from Lake St. Louis Boulevard to Route Z – asphalt overlay. This work began in the summer of 2011 and was completed in fall 2011.
Interstate 70 south outer road between Cave Springs and Route 370 – asphalt repair and paving. This work was completed in the fall of 2011.
Route 79 at Hackman, Route Y, Vomund and Dyer Roads - Install northbound left turn lanes. This work is expected to start in late summer 2012 and will continue into spring 2013.
Route 94 from west of Route D to Defiance – shouldering and resurfacing work. This work began in spring 2011 and was completed in fall 2011.
Route 364, west of Harvester Road to Mid Rivers Mall Drive. Extending Route 364 and the one-way outer road system. This project will construct bridges at Woodstone, Jungermann Road, Central School Road, Kisker Road and Mid Rivers Mall Drive, as well as one way outer roads along the corridor. Route 94 traffic expected to move onto the one-way outer roads between Woodstone and Harvest Drive by spring 2011 so construction on the Route 364 bridge over Jungermann Road can begin. By fall 2011 the outer road system from Harvest Drive to Mid Rivers Mall Drive is expected to be complete and Route 94 traffic will be moved to this new pavement to allow for Route 364 pavement and bridge work between Harvest and Mid Rivers Mall Drive to move into full gear. Project completion is expected in the fall of 2012.
Route B at Dardenne Creek – Bridge reconstruction. Crews will close the roadway for about 50 days to remove and replace the driving surface and paint the bridge. Work began in the spring of 2011 and was completed in summer 2011.
Route D from Route 94 to Route DD – shouldering and resurfacing work. Work began in spring 2011 and was completed in fall 2011.
Route P from Route 61 to Hoff Road – roadway widening and asphalt overlay. Work began in the summer of 2011 and was completed in fall 2011.
Route DD from Sommers to Route D -- roadway widening and asphalt overlay. Work began in summer 2011 and was complted in the fall of 2011.
Old Route 94 and Muegge - roadway widening. This project will add one lane in each direction to Muegge and will start in July 2011. St. Charles City will be making improvements to Old Route 94, upgrading the right turn from Old Route 94 to Muegge. This project is among the roadway improvements needed to ease traffic flow during the Blanchette Bridge renovation work. The additional lanes opened in fall 2011.
Back to Topics
FOR MORE INFORMATION, CONTACT:
St. Charles County Area Engineer Tom Evers at 1-888 ASK MODOT (275-6636)
Project Manager Tim Schroeder at 1-888 ASK MODOT (275-6636)
Community Relations Coordinator Linda Wilson at 1-888 ASK MODOT (275-6636) |