Route 36 Project Information
|
Pictures and videos of progress |
 |
Receive email updates on this project |
| |
| MoDOT has committed to upgrade to four lanes by the end of 2009. The project is divided into 3 sections: |
| |
Hannibal to Monroe City
- Project 100% complete
- Opened to traffic Aug. 7.
- Progressive Contractors, Inc., St. Michael, MN
- Award Cost $17,454,758.14
- The east exit to Monroe City is permanently closed.
See Northeast District Homepage for roadwork, lane closures and traveler information |
| |
Monroe City to Shelbina
-
Project 35% complete - Paving operations shut down for winter from Monroe City to the west. Other crews will be installing rock lining and erosion control, and seeding in various locations. (updated 12/03/08)
-
November 2009 completion
-
Monroe City to Hunnewell – New westbound lanes
- Progressive Contractors, Inc., St. Michael, MN
- Award Cost $22,847,487.81
|
| |
Shelbina to Macon
See North Central District Homepage for roadwork, lane closures and traveler information |
| |
Traffic During Construction
- Access to the highway through at-grade intersections
- Median openings will be provided at state routes and county roads
- Traffic maintained on the existing Route 36 during construction
- Temporary side road closures will be required occasionally
- MoDOT will make every effort to minimize inconvenience to drivers
|
| |
Schedule
|
| |
Cost/Funding
- Project construction is estimated at $100 million.
- Partially funded through a half-cent local sales tax in Macon, Shelby, Monroe and Marion counties - this is estimated to fund $43 million of the project
- $7 million earmark for Route 36 from Congressman Kenny Hulshof
- The other $50 million of the project (for construction) is being funded by MoDOT. All other project costs, including engineering, right of way acquisition, survey, etc., are being funded by MoDOT.
|
| |