Value Engineering Program

Home | About Us | VECP | VE Links | Helpful Documents | VE Contacts

bridgeConstruction VE
Beginning in late 1989 (Federal Fiscal Year 1990) the department added a construction value engineering program. Contractors submit Value Engineering Change Proposals (VECP'S) for department review and approval.

If accepted, the contractor and the department share the total savings on a 50/50 basis. Beginning in 2007, contractors can submit VE/Practical Design Underruns (VE/PDU's). 

If accepted, VE/PDU savings are split 25% Contractor/75%.  MoDOT  VE/PDU's typically consist of an existing feature that could remain a part of the final project, for example, exisiting pavement, an existing pipe, etc. See file below for a summary of the Federal Fiscal Year 2007 Construction VECP's and VE/PDU's.